System Restoration & Blackstart Resources (EOP-005 & EOP-006) on the NERC RC Exam: Test Tips and 5 Practice Questions

Why System Restoration Shows Up on Every NERC RC Exam

Restoration is one of the highest-stakes topics in the control room and one of the most heavily tested areas on the Reliability Coordinator (RC) exam. When the Bulk Electric System (BES) partially or fully collapses, EOP-005 (Transmission Operator restoration) and EOP-006 (Reliability Coordinator restoration coordination) define who does what, who approves the plan, and how blackstart resources are tested and maintained. Expect several questions on restoration plan authority, blackstart resource testing intervals, and the RC's coordination role across multiple TOPs.

Test Tips: How the Exam Frames Restoration

  • Know who owns which plan. Under EOP-005, the Transmission Operator (TOP) develops and maintains the restoration plan for its area. Under EOP-006, the Reliability Coordinator (RC) maintains a restoration plan for coordinating restoration across the TOPs in its RC Area. Confusing these two is the #1 trap.
  • The RC approves the TOP's restoration plan. EOP-005 requires the TOP's restoration plan to be approved by its RC. If a question asks who signs off on the TOP plan — it is the RC, not the BA and not FERC.
  • "Coordinate" vs. "direct." During restoration the RC coordinates restoration activities between TOPs and BAs. The TOP directs restoration within its own footprint. Watch verbs carefully in stem language.
  • Blackstart resource testing is periodic and documented. EOP-005 requires the TOP to verify blackstart resource capability on a defined schedule, and to have the generator owner/operator provide test results. If a blackstart resource fails a test, the TOP must notify the RC and address the plan gap.
  • Training and drills are required. Both EOP-005 and EOP-006 require periodic training on the restoration plan for personnel with restoration responsibilities, and a system restoration drill or exercise on a recurring basis. Expect a question on "how often does the RC exercise its restoration plan?"
  • Most Conservative Action still applies. If restoration coordination between RCs or TOPs breaks down or communications are lost, operators take the most conservative action to preserve reliability — do not wait for permission.

5 Practice Questions

  1. A Transmission Operator has completed its annual update to the restoration plan. Under EOP-005, who must approve the updated plan before it becomes effective?

    • A. The Balancing Authority
    • B. The Reliability Coordinator
    • C. FERC
    • D. The Generator Operator whose units are designated blackstart
  2. During a widespread outage, two Transmission Operators in the same RC Area disagree on the sequence for re-energizing a shared 500 kV path. Which entity is responsible for coordinating the restoration between them?

    • A. The Generator Owner of the blackstart unit
    • B. The Balancing Authority
    • C. The Reliability Coordinator
    • D. The Planning Coordinator
  3. A blackstart resource fails its periodic capability verification. Under EOP-005, what is the Transmission Operator's obligation?

    • A. Remove the resource from the restoration plan permanently with no further action
    • B. Notify its Reliability Coordinator and address the impact to the restoration plan
    • C. Wait for the next annual plan revision to update documentation
    • D. Immediately declare an Energy Emergency Alert
  4. Which of the following best describes the Reliability Coordinator's restoration responsibility under EOP-006?

    • A. Directing switching orders inside each TOP's footprint
    • B. Owning and testing blackstart generation
    • C. Maintaining a plan to coordinate restoration activities between TOPs and BAs in its RC Area
    • D. Approving each Generator Operator's startup procedure
  5. During restoration, the RC loses voice and data communications with one of its Transmission Operators. What is the most appropriate action for the TOP's on-shift operator?

    • A. Halt all restoration activity until communications are restored
    • B. Continue restoration per the approved plan and take the most conservative action to preserve reliability, while attempting to restore communications
    • C. Transfer restoration authority to the Balancing Authority
    • D. Wait for FERC guidance before proceeding

Answer Key & Explanations

  1. B — The Reliability Coordinator. EOP-005 requires each TOP's restoration plan (and updates to it) to be approved by the TOP's Reliability Coordinator. The BA does not approve TOP restoration plans; FERC does not approve individual operating plans.
  2. C — The Reliability Coordinator. EOP-006 places the coordination of restoration between TOPs (and between the RC's TOPs and BAs) with the RC. The RC does not run each TOP's internal switching, but it resolves cross-TOP sequencing and interface issues.
  3. B — Notify the RC and address the plan gap. EOP-005 requires the TOP to verify blackstart resource capability on the defined schedule and to act on the results. A failed test does not automatically remove the resource forever, and it is not by itself an EEA condition — but the RC must be informed and the restoration plan updated to reflect actual capability.
  4. C — Maintain a plan to coordinate restoration between TOPs and BAs in its RC Area. That is the plain-language description of the RC's EOP-006 responsibility. Blackstart ownership and internal switching are TOP/GO/GOP scope.
  5. B — Continue per the approved plan and take the most conservative action. Restoration does not stop because a communication path fails. Operators execute the approved restoration plan and default to the action that best preserves BES reliability while working to re-establish communications, consistent with the Most Conservative Action principle used across the NERC RC standards.

Take the Next Step

Restoration questions are where a lot of RC candidates lose points because the RC/TOP boundary is easy to blur under pressure. If you want structured drills, cited standard walk-throughs, and full-length RC practice exams built by control-room operators, explore EPG Solutions' NERC RC exam prep resources at epgsolutions.services. Study like you're going to sit the console the next morning — because that's what the exam is really testing.