Grid Pulse | June 24, 2026 — FERC Puts All Six RTOs on the Clock Over Large-Load Tariffs

Data-center large load, nearby generation and transmission studied under new grid tariffs

June 24, 2026 | Source: FERC — "FERC Launches Aggressive Targeted Action to Speed Large Load Integration," June 18, 2026 open meeting (Docket Nos. EL26-67 through EL26-72)


FERC Puts All Six RTOs on the Clock Over Large-Load Tariffs

At its June 18 open meeting, FERC issued show-cause orders under Section 206 of the Federal Power Act to all six organized markets: PJM (EL26-67), SPP (EL26-68), NYISO (EL26-69), MISO (EL26-70), CAISO (EL26-71), and ISO-NE (EL26-72).

Each grid operator and its transmission owners now have 60 days to do one of two things: show why their current tariffs remain just and reasonable without large-load-specific provisions, or file the tariff changes needed to address the gaps the Commission identified.

FERC also directed each operator to submit an informational report explaining how it will ensure adequate generation is available to serve both existing load and the new large loads lining up to connect.


What This Means in the Control Room and the Compliance Shop

This is no longer a rulemaking that lives in a comment docket. The 60-day clock is running, and it lands on the operators—not just on data center developers. Tariff teams, transmission planners, and interconnection groups are now drafting filings on a hard deadline.

The generation-adequacy report is the part reliability coordinators should watch. FERC is effectively asking each RTO to put on the record how it keeps resource adequacy intact while tens of gigawatts of flexible, fast-ramping load show up—the same load behavior NERC flagged in its May Level 3 alert on computational loads.

Expect ripple effects in study queues, large-load curtailment and flexibility terms, and cost-allocation language. If you sit in operations, planning, or compliance, the assumptions you brief from this summer may change before the snow flies.


EPG Solutions Can Help

When six RTOs file reforms inside the same 60-day window, the hard part is seeing how your market's approach stacks up against the others. EPG Solutions' benchmark intelligence reports track large-load interconnection rules, curtailment terms, and resource-adequacy positions across PJM, MISO, SPP, CAISO, ISO-NE, and NYISO—so your team walks into the next planning meeting already knowing where the lines are being drawn. Visit EPG Solutions → epgsolutions.services